Mill Creek Project Update 5/15/2026
May 15, 2026
As of today, the project is progressing well. We want to inform you of upcoming work and its impact on traffic:
- On May 16th, Sargent will perform grading and compacting in preparation for paving scheduled to begin on Monday.
- During paving, expect significant delays for traffic accessing Pierces Pond and Mill Creek roads as the new hot top needs to be allowed cool-down time.
- Traffic will be reduced to a single lane, with longer wait times at the intersection where initial pavement is laid.
- Residents in the affected areas are encouraged to plan for early departures and later returns to minimize inconvenience.
- We advise others to avoid the area during paving operations if possible.
- The road will be closed on Wednesday, May 20th through the evening commute but will reopen for the morning commute on Thursday, May 21st.
- Following paving, single-lane traffic will continue intermittently as curbing and guardrail work are completed.
We appreciate the community’s patience and cooperation throughout this project. Your understanding helps us maintain safety and efficiency as we work together to improve the roads.
Thank you,
The Town of Penobscot Select Board
Harold. Sara. Vivian.